Renovating a Condo Kitchen in Toronto

In a condo, the kitchen answers to the building before it answers to you. What the Condo Act actually says, what real Toronto buildings ask for, the five design decisions the building makes for you, and how the whole kitchen gets up the elevator.

🏢 Condo Act & real building rules⏱ 12 min read🔄 Checked October 2026
Also in: 中文

The cabinets are chosen, the countertop is booked, and the property manager has just replied to your email asking for your contractor’s licence, a WSIB clearance certificate, a liability insurance certificate and a description of the work — and has mentioned that approval can take up to a month. Nobody brought any of this up while you were picking door colours. In a house, a kitchen is a matter between you, your contractor and sometimes the city. In a condo there is a fourth party, the corporation, and its paperwork sits in front of everything else.

00 Three rulebooks

A condo kitchen answers to three sets of rules, not one

Everything below comes from one of three places, and it helps to know which, because they are enforced by different people.

  • The Condominium Act, 1998The provincial frame. It defines the common elements as “all the property except the units”, sets out how an owner gets permission to change them (section 98), prohibits activity in a unit that causes unreasonable noise or is likely to damage the property (section 117), and makes you responsible for taking “all reasonable steps” to see that your contractors follow the building’s rules (section 119).
  • Your corporation’s declaration, by-laws and rulesWhere most kitchen-specific rules actually live. The Act lets a board make rules about the use of the units to promote safety or to prevent unreasonable interference with other owners, provided they are reasonable, and those rules are enforceable like by-laws. The Condominium Authority of Ontario puts it plainly: “Every condo corporation has its own declaration, by-laws and rules. These are generally different between each corporation but will have some similarities.”
  • The city and the Electrical Safety AuthorityBuilding permits for walls and plumbing, ESA notifications for electrical work, and the municipal noise by-law. These apply to a condo suite the same way they apply to a house — and the building’s rules sit on top.

The second rulebook is the one people skip, and it is the one the property manager will quote back to you. Ask management for the declaration, the by-laws, the rules and the renovation form before you order anything. Read the parts that mention renovations, alterations, contractors, noise, elevators, flooring and plumbing. It is an evening, and it decides more about your kitchen than the showroom does.

What they search at midnight “condo renovation rules toronto” — usually right after the management office has replied to a question that was meant to be a formality.

01 Who decides

Inside your unit, and everything else

A common assumption is that the Condo Act requires board approval for any renovation. It does not say that directly. The section people quote, section 98, is about changes to the common elements. Approval for work inside your unit comes from your own building’s declaration and rules — which, in practice, almost always ask for it. The Condominium Authority of Ontario’s guidance: “Unit owners generally must make a request to their board to have the renovation approved and may also need to have work approved by the municipality.”

How broad the requirement is depends on the wording. One downtown Toronto building’s renovation form (TSCC 2516) reads: “No wall, floor, door or window, toilet, bathtub, washbasin or sink, heating, air conditioning, plumbing or electrical equipment … shall be installed, removed, extended or otherwise altered in a unit … without the prior written consent of the Corporation.” Cabinets are not on that list. The sink is — and so are the floor, the plumbing and the electrical. A kitchen renovation that touches none of those is hard to imagine.

Then there is the line between your unit and the building. The CAO describes common elements as “shared areas of the condo property, like hallways, elevators, piping, amenities, etc.” Where exactly your unit ends is set by your declaration, so it varies, but shared drains and risers are the obvious candidates in a kitchen. A change to the common elements needs a board resolution and a written agreement with the corporation that is registered against your unit’s title, and that agreement “binds the owner’s unit and is enforceable against the owner’s successors and assigns” — in other words, the next owner inherits it.

What will not be approved

The CAO again: “Typically, any changes that impact the structural integrity of the building, contravenes the governing documents or affects other owners safety are not likely be approved.” In a concrete building, that line usually runs through the slab. Read section 03 before you draw an island.

02 The application

What the renovation application usually asks for

No two buildings use the same form, but the published policies we read for four Toronto corporations, and the CAO’s own summary, ask for the same handful of things. The CAO: “some condo corporations may require a formal process and application to be submitted, some may require insurance information from contractors, as well as pre and post inspections.”

  • Notice before work starts — “at least one week in advance” in one building’s form, alongside the written consent above.
  • Your contractor’s paperwork — the same form asks for “operating licence(s), their most up-to-date WSIB clearance certificate and their most recent copy of general comprehensive liability insurance.” Some corporations go further: “Some corporations may require owners to use approved contractors or have contractors work only during certain hours” (CAO).
  • A description of the work — what is being removed, installed, extended or altered. For floors, often a product specification (see the underlay numbers in section 03).
  • Inspections — a walk-through before and after the job, which one North York corporation (YCC 50) builds into its renovation agreement.
  • A refundable damage deposit and an indemnity — one building’s rules (TSCC 1536) ask for a security deposit and a written undertaking to indemnify the corporation for contractor work that affects the common elements.
  • Time — “This may take up to thirty (30) Calendar days,” warns one form. Apply before you order cabinets, not after.
Where a drawing earns its keep

“Renovate kitchen, new cabinets and counter” is the description that comes back with questions. A plan and a set of elevations answer most of them at once — what goes where, which wall, and above all that the sink is staying where the drain is. That is what our planner is for: draw the real room, place real catalogue cabinets at the sizes that exist, then ⬇ Export a PDF with the top view, the countertop dimension drawing, a 3D view and the elevations. It runs in a browser tab, it is free, and you can start without an account. It will not fill in your building’s form for you; it will make the attachment the form asks for.

03 Design limits

Five design decisions the building makes for you

These are the places where a condo kitchen stops being a design question and becomes a building question. Each one changes a cabinet, so settle them before the layout is final.

  • The sink stays close to its drainIn a house, a drain can usually be rerouted under the floor. In a concrete tower it generally cannot. TSCC 2516’s form is blunt: “All drain work for new plumbing fixtures must be installed above the concrete slab surface. Under no circumstances is the concrete to be chipped or cut.” A drain has to fall the whole way to the stack, so every foot you move the sink away from it is a pipe sloping through cabinets, a toe kick or a raised floor.What it means for the layoutSliding the sink a cabinet along the same wall is sometimes realistic. An island sink on the far side of the room usually is not. How sinks and their bases are sized.
  • The hood probably recirculatesYCC 50’s renovation agreement: “Hooded stove vents (only filters allowed) and nothing is to be vented into corporation’s ventilation system at all.” Not every building says that, but ask before you buy a hood, because a ducted hood and a recirculating one change the cabinet above the range in different ways.What it means for the layoutA recirculating hood needs filters you can reach and clean; a ducted one needs a route the building will allow. Hood heights and clearances.
  • The garburator may be bannedTSCC 2516: “Garburators may not be installed due to overloading of the stack lines and drain backups.” Some buildings cite the city for the same rule, but Toronto’s sewer by-law is narrower than that: it prohibits grinders whose effluent discharges into a storm or combined sewer. The building’s rule is the one that binds you, so ask.What it means for the layoutDo not plan the sink base around one until the answer is yes in writing.
  • The floor has an acoustic numberIf new flooring goes in with the kitchen, the building will likely specify the underlay. In the published rules and tribunal records we read for five Toronto-area buildings, the minimum ratings ran from 55 to 70 (IIC, or the field-tested FIIC) — there is no single Toronto standard. Get your building’s number before you buy flooring.What it means for the layoutFloor first or cabinets first changes the height of everything; floating floors must never be pinned under cabinets. The order a kitchen gets done in.
  • The water is not yours to turn offIn one building, “A request for a plumbing shut down must be provided to the Management Office, with no less than (3) days’ notice. Shut downs, are only permitted Monday to Friday, 9am - 3pm.” Disconnecting the old sink and connecting the new one are booked appointments, not afternoons.What it means for the scheduleBook the shut-offs when you book the countertop installation, since the sink goes in after the stone.

Condo kitchens are usually small and often a single wall or a galley, so every inch of the run counts. Small kitchen layouts that work.

04 Logistics

Getting a kitchen up the elevator

Everything — the cabinets, the countertop, the appliances, the tools and the old kitchen on its way out — goes through the service elevator, and the elevator has a calendar. One building’s form: “Resident must book the service elevator with the Front Desk for transport of all large loads of tools, equipment and/or materials or for the removal of debris.” Another asks for the booking “no less than three (3) days in advance, so that elevator pads on the day of renovations, can be installed.” A third wants the concierge to inspect the elevator “immediately prior to using” it, with protective pads in place.

  • Measure the route, not just the room — the elevator door’s width and height, the cab’s inside depth, height and diagonal, the tightest corridor turn and your suite door. Write the numbers on the plan.
  • Find the long pieces — tall pantry and oven cabinets, finished end panels and the longest countertop section are the items that do not fit everywhere. Flat-packed cabinets travel as cartons and are built in the suite; an assembled tall cabinet is the one that refuses to turn a corner. Flip cabinets ship flat-packed unless you choose assembly.
  • Ask the fabricator about the stone — will the longest piece fit in the cab? If not, the answer is a seam, and you want to choose where it goes rather than discover it on installation day. How the countertop materials compare.
  • Book each heavy day — cabinet delivery, demolition debris, countertop installation and appliance delivery are separate elevator bookings, and someone has to be there for each.
  • Plan the debris out — the building’s chutes and bins are not for it. One form: “Corporation garbage chutes, garbage and recycling bins are for household garbage only.” Another makes the contractor responsible for “removing all construction debris and garbage from the suite off site.” What to do with the old cabinets.
05 Work hours

The city sets the outer edge; the building sets the real one

Toronto’s noise by-law (Municipal Code Chapter 591) prohibits clearly audible construction noise from 7 p.m. to 7 a.m. on weekdays, before 9 a.m. and after 7 p.m. on Saturdays, and all day on Sundays and statutory holidays — and its definition of construction equipment includes “hand tools, power tools.” Condo rules are often narrower. These are the hours from published rules of three Toronto buildings:

SourceWeekdaysSaturdaySundays & holidays
City of Toronto by-law7 a.m.–7 p.m.9 a.m.–7 p.m.No construction noise
TSCC 2516 (downtown)9–5; heavy or noisy work 10–59–5; heavy or noisy work 10–5No work
YCC 50 (North York)9 a.m.–7 p.m.10 a.m.–6 p.m.Not listed
TSCC 1519 (Yorkville)Noisy work 9–5No noisy workNo noisy work

On top of both, the Condo Act prohibits unreasonable noise in a unit no matter what the rules say. Outside Toronto, Mississauga, Markham, Vaughan and the other GTA municipalities each have their own noise by-laws, and the building’s rules still apply on top. Plan the loud days — demolition, drilling for the wall rail, cutting filler strips — inside the building’s window, and do the quiet work, like assembling flat-pack boxes and adjusting hinges, around it.

06 Permits

The city and the ESA still apply

Board approval is not a building permit, and a building permit is not an electrical notification. Toronto’s own list of work that does not need a building permit includes “Installation of cabinetry and millwork” and “Repairing and replacing plumbing fixtures.” Its list of work that does includes alterations “such as adding or removing walls” and work to “Install or modify heating and or plumbing systems.” The CAO summarises the same idea: “Typically, municipalities require permits for renovations requiring structural changes, modifications to plumbing and electrical systems and exterior changes.”

Electrical work is a separate track run by the Electrical Safety Authority, not the city. In ESA’s words: “Having a building permit isn’t the same as filing an electrical notification. You may need both.” ESA allows owners to do electrical work in their own home if they file a notification, and says that if you hire someone, “it must be a Licensed Electrical Contractor.” A condo can be stricter: TSCC 2516 requires a licensed electrician and a copy of the passed ESA permit, and a licensed plumber for all plumbing.

The full permit picture for Ontario and the GTA, city by city.

07 Damage

Who pays if something leaks

A kitchen is where a condo renovation is most likely to put water where it should not be, and the Act is specific about the money. If an owner, or someone living in the unit, “through an act or omission causes damage to the owner’s unit,” the lesser of the repair cost and the corporation’s insurance deductible is added to that unit’s common expenses (section 105) — and a by-law can widen that. Your contractor’s mistakes are your responsibility to the building too, because section 119 makes you take reasonable steps to see that your agents comply with the rules.

The new kitchen itself may not be covered by the building’s policy at all. The corporation’s duty to repair after damage “does not include the obligation to repair after damage improvements made to a unit,” and its duty to insure excludes them too. What counts as an improvement is measured against your building’s standard unit definition. The CAO: “Owners are responsible for decorative and non-standard unit elements,” and an owner’s insurance “would need to cover improvements made to their unit.” Ask management for the standard unit definition, then call your insurer before demolition, not after.

08 Before you order

The list to clear before anything is ordered

  • Declaration, by-laws, rules and the renovation form — from management, read, with the renovation and contractor sections marked.
  • The standard unit definition — so you know what your own insurance has to cover.
  • Answers in writing — hood venting, garburator, flooring underlay rating, work hours, elevator booking, debris, water shut-off notice, contractor documents.
  • A drawing that keeps the sink near its drain — plan and elevations, exported and attached to the application.
  • The route measured — elevator, corridor and suite door, against the tallest cabinet and the longest piece of countertop.
  • Written approval in hand — before demolition, and ideally before the cabinets are ordered, because the board can say no to the one change your layout depends on.
  • Insurance checked — yours, for the improvements, and your contractor’s, on the form the building wants.
  • The heavy days booked — delivery, debris, countertop, appliances and each water shut-off.

If every line is true, the rest of the job runs in the same order as any kitchen. Here is that order, step by step.

§ Sources

Where this comes from

Rules quoted from individual buildings are examples of common practice, not law, and they change; your own building’s documents are the ones that apply. Checked October 2026.

? People also ask

Straight answers

Do I need condo board approval to renovate my kitchen?+

Almost always, though the requirement usually comes from your building’s declaration and rules rather than directly from the Condo Act. The Condominium Authority of Ontario says unit owners “generally must make a request to their board to have the renovation approved and may also need to have work approved by the municipality.” Some buildings’ rules list sinks, plumbing, electrical and floors among the things that cannot be altered without written consent.

Does section 98 of the Condo Act apply to my kitchen?+

Section 98 covers changes to the common elements, not the inside of your unit. If your kitchen work touches the common elements, such as shared piping, it needs a board resolution and an agreement with the corporation registered against your unit, which binds future owners. Work inside the unit is controlled by your building’s declaration, by-laws and rules.

Can I move my kitchen sink in a condo?+

Sometimes a short distance, rarely far. In concrete buildings the drain usually cannot be buried in the slab; one Toronto building’s rules require all new drain work to sit above the concrete and forbid chipping or cutting it. A drain has to slope to the stack, so a sink moved along the same wall may work, while an island sink across the room usually does not. Ask management before you design around it.

Can I vent a range hood outside in a condo?+

It depends on the building. At least one Toronto corporation allows only recirculating hoods with filters and forbids venting into the building’s ventilation system. Ask before you choose the hood, because a ducted and a recirculating hood change the cabinet above the range differently.

What hours can I renovate in a Toronto condo?+

The city’s noise by-law allows construction noise from 7 a.m. to 7 p.m. on weekdays and 9 a.m. to 7 p.m. on Saturdays, and none on Sundays and statutory holidays. Condo rules are often narrower: published rules we read set hours such as 9 to 5 on weekdays, with heavy or noisy work limited further. Your building’s rules are the ones you will be held to.

Do I need a city permit to renovate a condo kitchen in Toronto?+

For cabinets alone, generally not: Toronto lists installing cabinetry and millwork and replacing plumbing fixtures as work that needs no building permit. Adding or removing walls, or installing or modifying plumbing, does. Electrical work is reported separately to the Electrical Safety Authority, and many buildings require licensed trades for both plumbing and electrical.

Who pays if my kitchen renovation causes a leak in my condo?+

Under section 105 of the Condo Act, if an owner or occupant causes damage to their unit, the lesser of the repair cost and the corporation’s insurance deductible is added to that unit’s common expenses, and a by-law can extend this. The corporation also does not insure or repair improvements to a unit, so your own policy needs to cover the new kitchen.

Will flat-pack cabinets fit in a condo elevator?+

Flat-packed cabinets travel as cartons and are assembled in the suite, which is usually easier than moving built cabinets. The pieces to check are the long ones: tall pantry or oven cabinet sides, end panels and the longest countertop section. Measure the elevator door and cab, including the diagonal, before you order, and book the service elevator for delivery.

How long does condo renovation approval take?+

It varies by building. One Toronto corporation’s form warns that approval may take up to thirty calendar days. Apply before the cabinets are ordered, so a refusal of one detail does not strand an order.

Your turn

Draw it around the drain you have.

Plan the kitchen around the sink position the building will allow, check it in plan, 3D and elevation, and export the drawings your application asks for. Free, in a browser.

Open the 3D planner →